Change a project's SAST tool version

The version of Coverity used for static analysis can be modified at the organization, application, project, and branch level. To change a project's Coverity version, follow these steps:

Note: Only Organization Administrators, Organization Application Managers, Application Administrators, Application Contributors, and other users with permissions to manage project settings can complete these steps.
  1. Go to Portfolio, open an application, and open a project.
  2. Go to Settings > Analysis.
  3. Under SAST Analysis, select Edit.
  4. Select the appropriate Coverity version, as required.
    • To use the latest supported version of Coverity, select Automatically use latest version (recommended).

      Selecting this option ensures that the project always uses the most recent supported version of Coverity. When a new version of Coverity is available, the project will automatically use it for SAST tests.

    • To use a specific version of Coverity, select Use a specific tool version, and select the appropriate version from the dropdown.
      Important: Here, you can select the latest supported version of Coverity, or a deprecated one. When you choose a specific version of Coverity, the version assigned to the project will not change when a new version of Coverity is added to Polaris, even if support for the version you selected is removed. When support for a version of Coverity ends, SAST tests that attempt to use the unsupported version will not run. To resume testing, you must activate a supported version of Coverity.
  5. Select Save.
Important: After you change a project's Coverity version, a full SAST test must be performed on at least one branch in the project before rapid SAST tests can run.